1-1 | Who Performs Inspections and How Often?

As a starting point, the same work practices which apply to all “working” wire rope apply to wire rope which has been fabricated into a sling. Therefore, a good working knowledge of wire rope design and construction will not only be useful, but essential in conducting a wire rope sling inspection.

There are two industry standards that exist to provide the end-user with guidelines for inspection and criteria that warrants removal from service: OSHA 1910.184 and ASME B30.9.

Who Performs Wire Rope Sling Inspection

Initial Inspection (Prior to Initial Use):

Best practice is to inspect the wire rope sling upon receiving it from the manufacturer. Double-check the sling tag to make sure it’s what you ordered and that the rated capacity meets all of your project specifications and lifting requirements.

Frequent (Daily or Prior to Use):

Designate a Competent Person to perform a daily visual inspection of slings and all fastenings and attachments for damage, defects, or deformities. The inspector should also make sure that the wire rope sling that was selected meets the specific job requirements it’s being used for.

Users can’t rely on a once-a-day inspection if the wire rope sling is used multiple times throughout the day. Damage to wire rope can occur on one lift and best practice is to perform a visual inspection before any shift change or changes in lifting application. Because shock loads, severe angles, sharp edges, and excessive heat can quickly cause damage to a lifting sling, the user should inspect the sling prior to each lift.

Periodic Inspection:

A documented periodic inspection is performed by either a professional service provider, or by a Qualified person every 12 months (at a minimum) and monthly to quarterly in more severe service conditions. The following are all determining factors in scheduling the frequency of a periodic inspection:

  • Frequency of use
  • Severity of service conditions
  • Nature of the lifts being performed
  • Experience gained on the service life of wire rope slings used in similar applications

ASME provides these additional periodic inspection guidelines based on the service of the wire rope sling:

  • Normal Service – Yearly
  • Severe Service – Monthly to Quarterly
  • Special Service – As recommended by a Qualified person

Depending on the severity of the operating environment and frequency of use, your business may decide that a more thorough inspection should occur more often than the minimum yearly requirement. Periodic inspections are required to be documented per ASME B30.9 and records retained.

The employer is required to maintain a record of the most recent thorough sling inspection—however, individual records for each sling that was inspected are not required. Failure to maintain and retain inspection records is one of the most common issues we see that can prevent a company from reaching full OSHA compliance.